When a Charging Station Permit Is Required
Installing an electric vehicle charging station on public land or in areas open to public use (e.g. condominium courtyards with external access, open car parks) always requires municipal authorisation. This applies both to public infrastructure and to charging points intended for private use but accessible to the public, such as those installed by businesses, accommodation facilities or condominium management.
Upgrades or replacements of existing charging stations may also require a new application, especially if the location, power output or land-use conditions change.
Applications to install electric vehicle charging points on public land can only be submitted by authorised CPOs (charging point operators).
What the EV Charging Station Permit Covers
The municipal permit allows the charging station to be installed in compliance with the relevant technical, planning, building and electrical regulations. It ensures that the charging point is safe, properly signposted, accessible and compliant with energy management requirements.
It also governs any permanent or temporary occupation of the land and may include the option to reserve a parking space dedicated exclusively to charging. Without this permit, even private infrastructure visible from the street can be considered unauthorised.
Who This Service Is For
Our service is designed for anyone who wants to install charging points in public or semi-public spaces:
- Private individuals and condominiums wanting to install a charging station in front of the building or in shared areas with public access.
- Businesses and accommodation facilities wanting to offer charging services to their customers.
- Electric mobility infrastructure providers installing and managing shared-use charging points.
- Condominium administrators and appointed technicians responsible for property or facilities management.
What Our Full Service Includes
We handle every stage, technical and administrative, of the permit application:
- Technical site survey to assess feasibility and any existing constraints on the installation area.
- Preliminary design and feasibility study, with tailored solutions based on the location and type of charging station.
- Completion and submission of municipal forms, including any required technical attachments.
- Full management of the permit process with the municipality, through to the issuing of the clearance.
- Coordination with energy providers or electric mobility operators for installation and activation.
Our service is designed to simplify the entire process and reduce waiting times.
Documents Required
Depending on the area and type of installation, the following documents may be required:
- Site plan showing the exact installation point.
- Technical report detailing the charging station’s specifications and intended use.
- Applicant’s ID document (private individual, legal representative or technician).
- SCIA notification, if applicable for commercial activities, or authorisation from the condominium.
- Specific municipal form, prepared by us together with all supporting technical documentation.
Timeframes and Costs
Average processing times range between 15 and 30 working days, depending on the area, the completeness of the documentation and any planning restrictions.
Costs may include:
- Public land occupation fee, if the installation is permanent or on state-owned land.
- Application processing charges and administrative fees.
- Technical costs for design and case management.
We provide transparent, tailored quotes before starting the process.
What Happens Without a Permit
Installing a charging station without a permit carries real risks:
- The installation is considered unauthorised, with the possibility of forced removal by the municipality.
- Administrative penalties and an obligation to restore the area.
- Exclusion from incentives or bonuses linked to electric mobility.